I'm struggling to apply rate and reserves multipliers within a Planned Change to modify my well potentials.
If I try and do it form the planned change window the well specific tab is greyed out
And trying to do it via the show planned changes button on the edit node properties window it then does not save the changes im making in the Rate Multiplier filed in the Planned Changes Table.
------------------------------------------------------------------------------------------------------------------------------------------------------------------------
If the Planned Change applies to a node, then the multipliers are not applicable and are greyed out. If the Planned Change applies to a well, then the multilpliers can be set.
So the first thing to do is to check that your Planned Change (for the multipliers) applies to the MacC well, not the node it flows to.